# The Thurrock Flexible Generation Plant Consent (Amendment) Order 2023, Article 3: Amendments to Schedule 1 (Authorised Development)


In Schedule 1 to the 2022 Order (Authorised Development), in the description of Work no. 1 in 1B replace “with a net rated electrical output of up to 150 MW for four hours consisting of” with “having a combination of net rated electrical output and duration that delivers an electrical capacity of up to 600MWh, which may comprise—
(i) a net rated electrical output of 150MW for up to 4 hours
(ii) a net rated electrical output of 240MW for up to 2 hours and 30 minutes;
(iii) a net rated electrical output of 300MW for up to 2 hours;
(iv) a net rated electrical output of 400MW for up to 1 hour and 30 minutes; or
(v) a net rated electrical output of 600MW for up to 1 hour; and which consists of;

---
Source: https://www.legislation.gov.uk/uksi/2023/289/article/3 (the official version)
Page: https://openlegislation.uk/thurrock-flexible-generation-plant-consent-amendment-order-2023/article-3