# The Thurrock Flexible Generation Plant Development Consent Order 2022, Paragraph 10: Surface and foul water drainage

Extent: E+W+S

(1) No part of the authorised development can commence until written details for that part have been submitted to and approved by the relevant planning authority.
(2) The details submitted under sub-paragraph (1) must include—
(a) the means of pollution control;
(b) connection points to existing drainage network with consideration to directing drainage away from the West Tilbury Main catchment; and
(c) ground raising and effects on the routing of flood waters.
(3) The details submitted under sub-paragraph (1) must be in accordance with the conceptual drainage strategy certified under article 38.
(4) The surface and foul water drainage system for the relevant part of the authorised development must be constructed and maintained in accordance with the approved details unless otherwise agreed in writing by the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2022/157/schedule/2/paragraph/10 (the official version)
Page: https://openlegislation.uk/thurrock-flexible-generation-plant-development-consent-order-2022/schedule-2/paragraph-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.