# The Thurrock Flexible Generation Plant Development Consent Order 2022, Paragraph 12: Contaminated land

Extent: E+W+S

(1) If contaminated land is found during permitted preliminary works or construction of the authorised development, no further development can be carried out in the affected area until an investigation and remediation scheme has been submitted to and approved by the relevant planning authority; and the scheme must include details of—
(a) how the contaminated land is to be identified and assessed;
(b) where remediation is required by the scheme, the remediation measures;
(c) timescales for carrying out the remediation measures; and
(d) any ongoing monitoring or mitigation requirements.
(2) Any remediation measures, monitoring or mitigation requirements identified in the investigation and remediation scheme mentioned in sub-paragraph (1) must be carried out in accordance with the approved scheme.

---
Source: https://www.legislation.gov.uk/uksi/2022/157/schedule/2/paragraph/12 (the official version)
Page: https://openlegislation.uk/thurrock-flexible-generation-plant-development-consent-order-2022/schedule-2/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.