# The Thurrock Flexible Generation Plant Development Consent Order 2022, Paragraph 13: Archaeology

Extent: E+W+S

(1) No part of the authorised development with the potential to affect buried archaeological assets can commence until for that part a written scheme of archaeological investigation of areas of archaeological interest has been submitted to and approved by the relevant planning authority following consultation with Historic England.
(2) The scheme approved under sub-paragraph (1) must be substantially in accordance with the outline written scheme of archaeological investigation, and identify the measures to be taken to investigate, protect, record or preserve any significant archaeological remains that may be found.
(3) Any archaeological works carried out under the approved scheme must be carried out by an organisation registered with the Chartered Institute for Archaeologists or by a member of that Institute.
(4) Any archaeological works must be carried out in accordance with the approved scheme.

---
Source: https://www.legislation.gov.uk/uksi/2022/157/schedule/2/paragraph/13 (the official version)
Page: https://openlegislation.uk/thurrock-flexible-generation-plant-development-consent-order-2022/schedule-2/paragraph-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.