# The Thurrock Flexible Generation Plant Development Consent Order 2022, Paragraph 23: Anticipatory steps

Extent: E+W+S

If before this Order comes into force the undertaker or any other person has taken any step in compliance with any requirement in Part 1 of this Schedule, that step may be taken into account to determine compliance with that requirement provided that step would have been a valid step for the purpose of the requirement if it had been taken after this Order came into force.

---
Source: https://www.legislation.gov.uk/uksi/2022/157/schedule/2/paragraph/23 (the official version)
Page: https://openlegislation.uk/thurrock-flexible-generation-plant-development-consent-order-2022/schedule-2/paragraph-23
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.