# The Thurrock Flexible Generation Plant Development Consent Order 2022, Paragraph 24: Submissions and approvals

Extent: E+W+S

(1) Where, under any requirement, approval of any plans, details, schemes or other documents is required, the plan, details, scheme or other documents submitted for approval must be in writing.
(2) Where under any requirement the approval or agreement of the discharging authority or another person is required, that approval or agreement must be provided in writing.
(3) A copy of any approval or amendment to an approval issued under these requirements by a discharging authority other than the relevant planning authority must be copied to the relevant planning authority at the same time as it is issued to the undertaker.

---
Source: https://www.legislation.gov.uk/uksi/2022/157/schedule/2/paragraph/24 (the official version)
Page: https://openlegislation.uk/thurrock-flexible-generation-plant-development-consent-order-2022/schedule-2/paragraph-24
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.