# The Thurrock Flexible Generation Plant Development Consent Order 2022, Schedule 6: LAND OF WHICH ONLY TEMPORARY POSSESION MAY BE TAKEN

Extent: E+W+S

(1)
Location
(2)
Plot Reference Number shown on land plans
(3)
Purpose for which temporary possession may be taken
(4)
Relevant part of the authorised development
Land Plans – Sheet 3
Road forming public highway and private road shown coloured yellow on the access, rights of way and traffic management plans
03/07
To allow a temporary diversion of a public right of way.
Work no.4
Station Road, Public Highway at Station Road, East Tilbury
03/10
To create a new access from the public highway including temporary partial closure of the highway and traffic management.
Work nos.4 and 5
Land Plans – Sheet 5
Fort Road, public
highway at Fort Road,
Tilbury
05/06
To allow the creation of a new access from the public highway including temporary partial closure of the highway and traffic management.
Work no.15
Fort Road, public
highway at Fort Road,
Tilbury
05/08
To allow the creation of a new access from the public highway including temporary partial closure of the highway and traffic management.
Work no.15

---
Source: https://www.legislation.gov.uk/uksi/2022/157/schedule/6 (the official version)
Page: https://openlegislation.uk/thurrock-flexible-generation-plant-development-consent-order-2022/schedule-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.