# The Thurrock Flexible Generation Plant Development Consent Order 2022, Paragraph 4: Road condition surveys

Extent: E+W+S

(1) The undertaker will notify the Council of—
(a) the anticipated date of commencement of development under this Order; and
(b) the anticipated construction programme and date of completion of the authorised development;
not less than 3 months prior to that anticipated date of commencement of development under this Order.
(2) The Council will provide a proposed scope setting out the number (having regard to the construction programme notified to it by the undertaker), content and format of road conditions surveys to the undertaker for comment no later than 4 weeks after being notified under sub-paragraph (1). The proposed scope will include live data monitoring to provide 24/7 speed and volume counts. The Council must have regard to any reasonable comments made by the undertaker within 2 weeks of receipt of that proposed scope in finalising the scope of the road conditions surveys.
(3) The first road condition survey must be undertaken prior to the anticipated commencement of HGV movements for the authorised development, and further surveys must be undertaken at 3 month intervals from the date of the first surveys until the completion of the construction phase of the authorised development. A final survey must be undertaken within 28 days of the Council being notified by the undertaker that the construction of the authorised development has been completed.

---
Source: https://www.legislation.gov.uk/uksi/2022/157/schedule/8/part/10/paragraph/4 (the official version)
Page: https://openlegislation.uk/thurrock-flexible-generation-plant-development-consent-order-2022/schedule-8/part-10/paragraph-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.