# The Thurrock Flexible Generation Plant Development Consent Order 2022, Paragraph 6: HGV route remediation

Extent: E+W+S

The undertaker must maintain and provide to the Council at 3 month intervals from the date of commencement of development under this Order until the authorised development is completed, records of the number of HGVs using the local highway to access the authorised development and details of which route such HGVs used.

---