# The Thurrock Flexible Generation Plant Development Consent Order 2022, Paragraph 7: Interpretation

Extent: E+W+S

The promoter must—
(a) at all times afford reasonable facilities to the engineer for access to a specified work during its construction; and
(b) supply the engineer with all such information as he may reasonably require with regard to a specified work or the method of constructing it.

---
Source: https://www.legislation.gov.uk/uksi/2022/157/schedule/8/part/6/paragraph/7 (the official version)
Page: https://openlegislation.uk/thurrock-flexible-generation-plant-development-consent-order-2022/schedule-8/part-6/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.