# The Tillbridge Solar Order 2025, Schedule 13: DOCUMENTS AND PLANS TO BE CERTIFIED

Extent: E+W+S

(1)
Document name
(2)
Document reference
(3)
Revision number
(4)
Date
Land and Crown Land Plans
EN010142/APP/2.2
1
September 2024
Works Plans
EN010142/APP/2.3
4
April 2025
Streets, Rights of Way and Access Plans
EN010142/APP/2.4
3
October 2024
Traffic Regulation Measures Plan
EN010142/APP/2.5
3
October 2024
Hedgerow Removal Plan
EN010142/APP/2.9
1
September 2024
Book of Reference
EN010142/APP/4.3
5
April 2025
Environmental Statement (other than those listed individually below)
EN010142/APP/6.1
0
April 2024
Environmental Statement Chapter 3: Scheme Description of the ES
EN010142/APP/6.1
3
January 2025
Environmental Statement Chapter 10: Water Environment
EN010142/APP/6.1
1
December 2024
Environmental Statement Chapter 12: Landscape and Visual Assessment
EN010142/APP/6.1
2
January 2025
Environmental Statement Chapter 13: Noise and Vibration
EN010142/APP/6.1
1
June 2024
Environmental Statement Chapter 18: Cumulative Effects and Interactions
EN010142/APP/6.1
4
April 2025
Environmental Statement Chapter 19: Summary of Significant Environmental Effects
EN010142/APP/6.1
1
December 2024
Technical Appendices (other than those listed individually below)
EN010142/APP/6.2
0
April 2024
Appendix 8-5-1: Principal Site Geophysical Report (Part 1)
EN010142/APP/6.2
1
June 2024
Appendix 8-5-2: Cable Route Corridor Geophysical Survey Report
EN010142/APP/6.2
1
June 2024
Appendix 9-5: Baseline Report for Great Crested Newts
EN010142/APP/6.2
1
June 2024
Appendix 9-12: Habitat Regulations Assessment Report
EN010142/APP/6.2
2
December 2024
Appendix 10-3: Flood Risk Assessment
EN010142/APP/6.2
2
January 2025
Appendix 10-4: Outline Drainage Strategy
EN010142/APP/6.2
0
April 2024
Appendix 12-6: LVIA Assessment of Visual Effects
EN010142/APP/6.2
1
December 2024
Appendix 12-7: Arboricultural Impact Assessment Part 1, 2 and 3
EN010142/APP/6.2
1
April 2025
Appendix 13-4: Noise Modelling
EN010142/APP/6.2
1
June 2024
Figures (other than those listed individually below)
EN010142/APP/6.3
0
April 2024
Figure 2-2: Environmental Constraints Plan
EN010142/APP/6.3
1
June 2024
Figure 3-1: Indicative Principal Site Layout Plan
EN010142/APP/6.3
2
April 2025
Figure 3-7: Access Locations
EN010142/APP/6.3
1
September 2024
Figure 3-12: Trenchless Crossing Cross Sections
EN010142/APP/6.3
1
October 2024
Figure 4-2: Outcome of Planning and Environmental Constraints Mapping
EN010142/APP/6.3
1
June 2024
Figure 4-3: Zones Suitable for Solar Development
EN010142/APP/6.3
1
June 2024
Figure 10-5: Watercourses, Flood Zones and Internal Drainage Boards
EN010142/APP/6.3
1
October 2024
Figure 12-4: A-H Zones of Theoretical Visibility
EN010142/APP/6.3
1
June 2024
Figure 12-5: Topography and Watercourses
EN010142/APP/6.3
1
December 2024
Figure 12-7: Public Rights of Way
EN010142/APP/6.3
1
December 2024
Figure 12-11: Local Landscape Character Areas (Defined by the Applicant)
EN010142/APP/6.3
1
June 2024
Figure 12-13: Q-V Reference Viewpoint Photography
EN010142/APP/6.3
0
June 2024
Figure 12-13: W-CC Reference Viewpoint Photography
EN010142/APP/6.3
0
June 2024
Figure 13-2: Operational Noise Contours
EN010142/APP/6.3
1
June 2024
Figure 16-3: Proposed HGV Routes – Principal Site and Cable Route Corridor
EN010142/APP/6.3
1
June 2024
Figure 16-4: Local Highway Network
EN010142/APP/6.3
1
June 2024
Figure 16-8: Selected Bus Stops and Routes Closest to the Scheme
EN010142/APP/6.3
1
June 2024
Figure 18-5: Transport Cumulative Traffic Routes
EN010142/APP/6.3
2
February 2025
Outline Design Principles Statement
EN010142/APP/7.4
3
January 2025
Framework Construction Environmental Management Plan
EN010142/APP/7.8
3
February 2025
Framework Operational Environmental Management Plan
EN010142/APP/7.9
4
April 2025
Framework Decommissioning Environmental Management Plan
EN010142/APP/7.10
3
February 2025
Framework Construction Traffic Management Plan
EN010142/APP/7.11
5
February 2025
Framework Soil Management Plan
EN010142/APP/7.12
2
April 2025
Framework Battery Safety Management Plan
EN010142/APP/7.13
1
January 2025
Framework Public Rights of Way Management Plan
EN010142/APP/7.16
1
December 2024
Framework Landscape and Ecological Management Plan
EN010142/APP/7.17
6
April 2025
Framework Skills, Supply Chain and Employment Plan
EN010142/APP/7.18
0
April 2024
Archaeological Mitigation Strategy
EN010142/APP/7.18
0
October 2024

---
Source: https://www.legislation.gov.uk/uksi/2025/1105/schedule/13 (the official version)
Page: https://openlegislation.uk/tillbridge-solar-order-2025/schedule-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.