  "url": "https://openlegislation.uk/tillbridge-solar-order-2025/schedule-15/paragraph-138",
  "json_url": "https://openlegislation.uk/tillbridge-solar-order-2025/schedule-15/paragraph-138.json",
  "legislation": "uksi/2025/1105",
  "legislation_title": "The Tillbridge Solar Order 2025",
  "legislation_url": "https://openlegislation.uk/tillbridge-solar-order-2025",
  "path": "schedule/15/paragraph/138",
  "kind": "paragraph",
  "number": "138",
  "heading": null,
  "text": "Prior to carrying out any works within the Order limits, Northern Powergrid must give written notice of the proposed works to the undertaker, such notice to include full details of the location of the proposed works, their anticipated duration, access arrangements, depths of the works, and any other information that may impact upon the works consented by the Order.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 15 para. 138 in force at 5.11.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/1105/schedule/15/paragraph/138",
    "retrieved_at": "2026-10-28T21:10:37.351261+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}