  "url": "https://openlegislation.uk/tillbridge-solar-order-2025/schedule-15/paragraph-195",
  "json_url": "https://openlegislation.uk/tillbridge-solar-order-2025/schedule-15/paragraph-195.json",
  "legislation": "uksi/2025/1105",
  "legislation_title": "The Tillbridge Solar Order 2025",
  "legislation_url": "https://openlegislation.uk/tillbridge-solar-order-2025",
  "path": "schedule/15/paragraph/195",
  "kind": "paragraph",
  "number": "195",
  "heading": null,
  "text": "Prior to the carrying out of any restricted works or any works authorised by this Order that will affect the apparatus, and if required by Exolum, the parties must use their reasonable endeavours to negotiate and enter into such deeds of consent (crossing consent) and (if considered necessary) variations to the existing rights upon such terms and conditions as may be agreed between Exolum and the undertaker acting reasonably and which must be no less favourable on the whole to Exolum than this Part of this Schedule, to the undertaker will use all reasonable endeavours to procure and secure the consent and entering into of such deeds and variations by all other third parties with an interest in the land at that time who are affected by such works.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 15 para. 195 in force at 5.11.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/1105/schedule/15/paragraph/195",
    "retrieved_at": "2026-10-28T21:10:37.351261+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}