Any protective works are to be constructed in land owned by the undertaker or in land in respect of which additional rights have been or are guaranteed to be granted to Exolum. The protective works shall be constructed in such manner and in such line or situation as may be agreed between Exolum and the undertaker or in default of agreement settled by in accordance with article 43 (arbitration).

---