# The Tillbridge Solar Order 2025, Paragraph 235: Co-operation and reasonableness

Extent: E+W+S

Where apparatus is required to be protected, altered, diverted or removed under this Part of this Schedule, the undertaker must use all reasonable endeavours to co-ordinate the execution of any works under this Part of this Schedule—
(a) in the interests of safety;
(b) in the interest of the efficient and economic execution of both Exolum’s works and the authorised development; and
(c) taking into account the need to ensure the safe and efficient operation of apparatus and carrying out of Exolum’s functions.

---
Source: https://www.legislation.gov.uk/uksi/2025/1105/schedule/15/paragraph/235 (the official version)
Page: https://openlegislation.uk/tillbridge-solar-order-2025/schedule-15/paragraph-235/enacted
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.