# The Tillbridge Solar Order 2025, Paragraph 24

Extent: E+W+S

The undertaker must make reasonable compensation for costs, charges and expenses which the drainage authority may reasonably incur—
(a) in the examination or approval of plans under this Part of this Schedule;
(b) in inspecting the construction of the specified work or any protective works required by the drainage authority under this Part of this Schedule; and
(c) in carrying out any surveys or tests by the drainage authority which are reasonably required in connection with the construction of the specified work.

---
Source: https://www.legislation.gov.uk/uksi/2025/1105/schedule/15/paragraph/24 (the official version)
Page: https://openlegislation.uk/tillbridge-solar-order-2025/schedule-15/paragraph-24
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

