# The Tillbridge Solar Order 2025, Paragraph 258: Co-operation

Extent: E+W+S

(1) Where in consequence of the proposed construction of any part of the authorised development, the undertaker or EDF requires the removal of apparatus under paragraph 252(2) or EDF makes requirements for the protection or alteration of apparatus under paragraph 254, the undertaker shall use its best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of EDF’s undertaking and EDF shall use its best endeavours to co-operate with the undertaker for that purpose.
(2) For the avoidance of doubt whenever EDF’s consent, agreement or approval is required in relation to plans, documents or other information submitted by the undertaker or the taking of action by the undertaker, it must not be unreasonably withheld or delayed.

---
Source: https://www.legislation.gov.uk/uksi/2025/1105/schedule/15/paragraph/258 (the official version)
Page: https://openlegislation.uk/tillbridge-solar-order-2025/schedule-15/paragraph-258
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

