# The Tillbridge Solar Order 2025, Paragraph 33: Notice of works

Extent: E+W+S

The undertaker must give to the engineer 30 days’ notice of its intention to commence the construction of any of the specified works or protective works, or, in the case of repair carried out in an emergency, such notice as may be reasonably practicable so that, in particular, the Canal & River Trust may where appropriate arrange for the publication of notices bringing those works to the attention of users of the Canal & River Trust’s network.

---
Source: https://www.legislation.gov.uk/uksi/2025/1105/schedule/15/paragraph/33 (the official version)
Page: https://openlegislation.uk/tillbridge-solar-order-2025/schedule-15/paragraph-33
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.