(1) After the purpose of any temporary works has been accomplished, the undertaker must with all reasonable dispatch, or after a reasonable period of notice in writing from Cottam requiring the undertaker to do so, remove the temporary works in, on, under, over, or within the Cottam Work Area.
(2) If the undertaker fails to remove the temporary works within a reasonable period of receipt of a notice pursuant to sub-paragraph (1), Cottam may remove the temporary works and may recover the reasonable costs of doing so from the undertaker.

---