# The Tillbridge Solar Order 2025, Paragraph 70

Extent: E+W+S

The undertaker must not exercise the powers conferred by this Order to prevent or interfere with the access by Gate Burton to the Gate Burton Work No. 4B Area.

---
Source: https://www.legislation.gov.uk/uksi/2025/1105/schedule/15/paragraph/70 (the official version)
Page: https://openlegislation.uk/tillbridge-solar-order-2025/schedule-15/paragraph-70
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

