# The Tillbridge Solar Order 2025, Paragraph 11: Archaeology

Extent: E+W+S

(1) The authorised development must be implemented in accordance with the archaeological mitigation strategy.
(2) No part of the authorised development may commence until a written scheme of archaeological investigation (which must accord with the archaeological mitigation strategy) for that part has been submitted to and approved by the relevant planning authority.
(3) For the purposes of sub-paragraph (2), “commence” includes any permitted preliminary works, excluding part (i) (advanced planting to allow for an early establishment of protective screening).
(4) Any archaeological works or archaeological monitoring and recording must be carried out in accordance with the approved scheme.

---
Source: https://www.legislation.gov.uk/uksi/2025/1105/schedule/2/paragraph/11 (the official version)
Page: https://openlegislation.uk/tillbridge-solar-order-2025/schedule-2/paragraph-11
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.