  "legislation": "uksi/2025/1105",
  "legislation_title": "The Tillbridge Solar Order 2025",
  "legislation_url": "https://openlegislation.uk/tillbridge-solar-order-2025",
  "path": "schedule/2/paragraph/18",
  "kind": "paragraph",
  "number": "18",
  "heading": "Operational noise",
  "text": "(1) No part of Work No. 1, Work No. 2 or Work No. 3 may commence until an operational noise assessment containing details of how the design of the authorised development has incorporated mitigation to ensure the operational noise rating levels as set out within Table 13-17 in Chapter 13 of the environmental statement are to be complied with for that part has been submitted to and approved by the relevant planning authority for that part.\n(2) The mitigation measures described in the operational noise assessment for each part of the authorised development must be implemented as approved and maintained throughout the operation of the relevant parts of the authorised development to which the plan relates.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 2 para. 18 in force at 5.11.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/1105/schedule/2/paragraph/18",
    "retrieved_at": "2026-10-28T21:10:37.351261+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}