# The Tillbridge Solar Order 2025, Part 5: TEMPORARY USE OF MOTOR VEHICLES ON PUBLIC RIGHTS OF WAY

Extent: E+W+S

(1)
Area
(2)
Public right of way
(3)
Measure
Lincolnshire County Council
Claimed PRoW Kexby and Willingham DMMO 680 between 12/01 and 13/01
Temporary use of motor vehicles under the direction of the undertaker at location PRoW 12/02 and PRoW 13/02 as shown on Sheets 12 and 13 of the streets, access and rights of way plans to facilitate the construction of the Scheme.
Lincolnshire County Council
Claimed PRoW DMMO 591 between 16/02 and 16/04
Temporary use of motor vehicles under the direction of the undertaker at location PRoW 16/02 and PRoW 16/04 as shown on Sheet 16 of the streets, access and rights of way plans to facilitate the construction of the Scheme.
Lincolnshire County Council
LL“Bram”66/1
Temporary use of motor vehicles under the direction of the undertaker at location PRoW 20/03 and PRoW 20/04 as shown on Sheet 20 of the streets, access and rights of way plans to facilitate the construction of the Scheme.
Nottinghamshire County Council
NT“South Leverton”BOAT 16
Temporary use of motor vehicles under the direction of the undertaker at location PRoW 21/01 and PRoW 21/02 as shown on Sheet 21 of the streets, access and rights of way plans, to facilitate the construction of the Scheme.
Nottinghamshire County Council
NT“Cottam”RB4
Temporary use of motor vehicles under the direction of the undertaker at location PRoW 21/03 and PRoW 21/04 as shown on Sheet 21 of the streets, access and rights of way plans, to facilitate the construction of the Scheme.
Nottinghamshire County Council
NT“Cottam”FP3
Temporary use of motor vehicles under the direction of the undertaker at location PRoW 21/05 and PRoW 21/06 as shown on Sheet 21 of the streets, access and rights of way plans, to facilitate the construction of the Scheme.
Nottinghamshire County Council
NT“Rampton”FP5
Temporary use of motor vehicles under the direction of the undertaker at location PRoW 23/01 and PRoW 23/02 as shown on Sheet 23 of the streets, access and rights of way plans, to facilitate the construction of the Scheme.
Nottinghamshire County Council
NT“Rampton”FP20
Temporary use of motor vehicles under the direction of the undertaker at location PRoW 23/06 and PRoW 23/07 as shown on Sheet 23 of the streets, access and rights of way plans, to facilitate the construction of the Scheme.
Nottinghamshire County Council
NT“Rampton”BOAT12
Temporary use of motor vehicles under the direction of the undertaker at location PRoW 23/08 and PRoW 23/09 as shown on Sheet 23 of the streets, access and rights of way plans, to facilitate the construction of the Scheme.

---
Source: https://www.legislation.gov.uk/uksi/2025/1105/schedule/6/part/5 (the official version)
Page: https://openlegislation.uk/tillbridge-solar-order-2025/schedule-6/part-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.