# The Town and Country Planning (Entertainment Resort Complex, Bedford) Special Development (No. 2) Order 2025, Paragraph 17: Broadmead Road


(1) Subject to sub-paragraph (2), construction traffic associated with authorised development may not use Broadmead Road as access for construction work other than preliminary work in the West Gateway Zone and Core Zone unless—
(a) a direct construction access point from Broadmead Road via the road known as Woburn Road to the West Gateway Zone has been constructed, and
(b) a signalised junction is operational at the intersection of Broadmead Road and the road known as Woburn Road that runs parallel to the A421.
(2) The restriction set out in sub-paragraph (1) does not apply to movements of heavy-duty vehicles associated with any construction work that it is necessary to carry out to provide the access or junction referred to in sub-paragraph (1)(a) or (b).

---
Source: https://www.legislation.gov.uk/uksi/2025/1322/schedule/3/paragraph/17 (the official version)
Page: https://openlegislation.uk/town-and-country-planning-entertainment-resort-complex-bedford-special-development-no-2-order-2025/schedule-3/paragraph-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.