# The Town and Country Planning (Entertainment Resort Complex, Bedford) Special Development (No. 2) Order 2025, Paragraph 55: Carbon management


(1) Authorised development must be carried out, and authorised works must operate, in substantial accordance with the principles and processes described in reference document 17 (carbon management plan).
(2) No later than one month after the date of Grand Opening, the site controller must provide to the Secretary of State a report setting out—
(a) how the class 1 and class 2 authorised works, construction of which was completed before the date of Grand Opening, have been constructed in compliance with sub-paragraph (1);
(b) how the experience of constructing those authorised works, and their subsequent operation, will inform future compliance with sub-paragraph (1).

---
Source: https://www.legislation.gov.uk/uksi/2025/1322/schedule/3/paragraph/55 (the official version)
Page: https://openlegislation.uk/town-and-country-planning-entertainment-resort-complex-bedford-special-development-no-2-order-2025/schedule-3/paragraph-55
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

