The matters referred to in regulation 12(2) are—
(a) the date by which the scoping information must be provided (being the date on which the relevant period for the purposes of regulation 12(4) ends);
(b) the effect of regulation 12(5) (suspension);
(c) the effect of regulation 50 (duration of suspension);
(d) the effect of regulation 51 (prohibition);
(e) the effect of regulation 12(6) (consultation prior to adoption of scoping opinion);
(f) the right conferred by regulation 12(8) (right to request scoping direction);
(g) the effect of regulation 12(9) (adoption of scoping opinion does not preclude right to require further information or evidence);
(h) the duty imposed on the applicant or, as the case may be, the operator, by regulation 46 (publicity);
(i) the right to challenge the notification and the time period for doing so.

---
Source: https://www.legislation.gov.uk/wsi/2009/3342/schedule/3/paragraph/4 (the official version)
Page: https://openlegislation.uk/town-and-country-planning-environmental-impact-assessment-undetermined-reviews-of-old-mineral-permissions-wales-regulations-2009/schedule-3/paragraph-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.