These Regulations substitute the saving and transitional provisions in paragraphs (2) to (6) of regulation 65 of the Town and Country Planning (Environmental Impact Assessment) (Wales) Regulations 2017 (“the 2017 Regulations”).

These Regulations also amend Schedule 2 to the 2017 Regulations to add the installation of certain overhead electric lines. The effect of this amendment is that an environmental impact assessment may need to be undertaken in respect of such development before planning permission is granted.

The Welsh Ministers’ Code of Practice on the carrying out of regulatory impact assessments was considered in relation to these Regulations. As a result, it was not considered necessary to carry out a regulatory impact assessment as to the likely costs and benefits of complying with these Regulations.