Regulation 56 Development in Wales likely to have significant effects in an EEA StateF8
England and Wales
Where—
it comes to the attention of the Welsh Ministers that development proposed to be carried out in Wales is the subject of an EIA application and is likely to have significant effects on the environment in F1an EEA State; or
F2an EEA State likely to be significantly affected by such development so requests,
the Welsh Ministers must—
send to the EEA State as soon as possible and no later than the date of publication in the London Gazette referred to in sub-paragraph (ii), the particulars mentioned in paragraph (2) and, if relevant, the information referred to in paragraph (3);
publish in a notice in the London Gazette the information in paragraph (2) and, if relevant, the information referred to in paragraph (3) and an address where additional information is available; and
give the EEA State a reasonable time in which to indicate whether it wishes to participate in the procedure for which these Regulations provide.
The particulars referred to in paragraph (1)(b)(i) are—
a description of the development, together with any available information on its possible significant effect on the environment in F3an EEA State; and
information on the nature of the decision which may be taken.
Where an EEA State indicates, in accordance with paragraph (1)(b)(iii), that it wishes to participate in the procedure for which these Regulations provide, the Welsh Ministers must as soon as possible send to that EEA State—
a copy of the application concerned;
details of the authority responsible for deciding the application;
a copy of any planning permission F4, infrastructure consent order or order made under section 90 of the 2024 Act relating to the development;
a copy of any environmental statement in respect of the development; and
relevant information regarding the procedure under these Regulations,
but only to the extent that such information has not been provided to the EEA State earlier in accordance with paragraph (1)(b)(i).
The Welsh Ministers must also ensure that the EEA state concerned is given an opportunity, before planning permission F5or infrastructure consent for the development is granted, to forward to the Welsh Ministers, within a reasonable time, the opinions of its public and of the authorities likely to be concerned by the project by reason of their specific environmental responsibilities on the information supplied.
The Welsh Ministers must F6...—
enter into consultations with the EEA State concerned regarding, inter alia, the potential significant effects of the development on the environment of that EEA State and the measures envisaged to reduce or eliminate such effects; and
determine in agreement with the F7... EEA State a reasonable period of time for the duration of the consultation period.
Where an EEA State has been consulted in accordance with paragraph (5), on the determination of the application concerned the Welsh Ministers must inform the EEA State of the decision and must forward to it a copy of the information referred to in regulation 28.
Annotations
Textual amendments
- F1
Word in reg. 56(1)(a) substituted (31.12.2020) by The Environmental Assessment of Plans and Programmes and the Environmental Impact Assessment (Miscellaneous Amendments) (Wales) (EU Exit) Regulations 2019 (S.I. 2019/245), regs. 1(2)(3), 6(11)(a); 2020 c. 1, Sch. 5 para. 1(1)
- F2
Word in reg. 56(1)(b) substituted (31.12.2020) by The Environmental Assessment of Plans and Programmes and the Environmental Impact Assessment (Miscellaneous Amendments) (Wales) (EU Exit) Regulations 2019 (S.I. 2019/245), regs. 1(2)(3), 6(11)(a); 2020 c. 1, Sch. 5 para. 1(1)
- F3
Word in reg. 56(2)(a) substituted (31.12.2020) by The Environmental Assessment of Plans and Programmes and the Environmental Impact Assessment (Miscellaneous Amendments) (Wales) (EU Exit) Regulations 2019 (S.I. 2019/245), regs. 1(2)(3), 6(11)(a); 2020 c. 1, Sch. 5 para. 1(1)
- F4
Words in reg. 56(3)(c) inserted (15.12.2025) by The Infrastructure (Wales) Act 2024 (Consequential, Transitional, Revocation and Saving Provisions) Regulations 2025 (S.I. 2025/1192), regs. 1(2)(b), 12(39)(a) (with reg. 12(44))
- F5
Words in reg. 56(4) inserted (15.12.2025) by The Infrastructure (Wales) Act 2024 (Consequential, Transitional, Revocation and Saving Provisions) Regulations 2025 (S.I. 2025/1192), regs. 1(2)(b), 12(39)(b) (with reg. 12(44))
- F6
Words in reg. 56(5) omitted (31.12.2020) by virtue of The Environmental Assessment of Plans and Programmes and the Environmental Impact Assessment (Miscellaneous Amendments) (Wales) (EU Exit) Regulations 2019 (S.I. 2019/245), regs. 1(2)(3), 6(11)(b)(i); 2020 c. 1, Sch. 5 para. 1(1)
- F7
Word in reg. 56(5)(b) omitted (31.12.2020) by virtue of The Environmental Assessment of Plans and Programmes and the Environmental Impact Assessment (Miscellaneous Amendments) (Wales) (EU Exit) Regulations 2019 (S.I. 2019/245), regs. 1(2)(3), 6(11)(b)(ii); 2020 c. 1, Sch. 5 para. 1(1)
- F8
Word in reg. 56 heading substituted (31.12.2020) by The Environmental Assessment of Plans and Programmes and the Environmental Impact Assessment (Miscellaneous Amendments) (Wales) (EU Exit) Regulations 2019 (S.I. 2019/245), regs. 1(2)(3), 6(11)(a); 2020 c. 1, Sch. 5 para. 1(1)