Regulation 5 Amendment to Schedule 1 to the 1989 Regulations
In Schedule 1 to the 1989 Regulations after paragraph 7A in Part I insert—
“7BWhere an application is made for the renewal of planning permission and—
(a)a planning permission has previously been granted for development which has not yet begun, and
(b)a limit as to the time by which the development must be begun was imposed under section 91 (limit of duration of planning permission) or section 92 (outline planning permission) of the Town and Country Planning Act 1990 which has not yet expired,
the fee payable in respect of the application shall be £60.”.