In these Regulations—

  • “the Act” means the Town and Country Planning (Scotland) Act 1997;

  • “active site” means a mining site where development relating to a mineral permission is being carried out to a substantial extent;

  • “inactive site” means a mining site which is not an active site;

  • “mineral permission” means planning permission for development consisting of, or including, surface coal mining;

  • “mining site” means—

    1. (a)

      where two or more mineral permissions relate to one area of land, the area of land which is being—

      1. (i)

        worked as a single site; or

      2. (ii)

        treated as a single site for the purposes of schedule 9 (review of old mineral planning permissions) or 10 (periodic review of mineral planning permissions) of the Act; and

    2. (b)

      in any other case, the land to which a mineral permission relates;

  • “monitoring report” means a report prepared by a planning authority setting out the results of a site visit;

  • “operator” means—

    1. (a)

      the person carrying out any development relating to a mineral permission on the land to which a mineral permission relates;

    2. (b)

      where there is more than one person carrying out development relating to a mineral permission, the person in overall control of the mining site; or

    3. (c)

      where there is no person who falls within a description in paragraph (a) or (b), the owner of the mining site;

  • “site visit” means entry by a planning authority, or a person authorised in writing by a planning authority, on to a mining site to—

    1. (a)

      ascertain whether there is or has been any breach of planning control on the site;

    2. (b)

      determine whether or to what extent any power conferred on the planning authority by Part 6 of the Act (enforcement) should be exercised in relation to the site; or

    3. (c)

      ascertain whether there has been compliance with any requirement imposed as a result of any such power having been exercised in relation to the site; and

  • “surface coal mining” means the winning and working of coal by means of the extraction of coal from the earth by removal from an open pit or borrow.