Development is permitted by Class A subject to the condition that before the end of the period of 24 months from the date when the mining operations have permanently ceased, or any longer period which the mineral planning authority agree in writing—

(a)

all buildings, plant or machinery permitted by this Class shall be removed from the land unless the mineral planning authority have otherwise agreed in writing; and

(b)

the land shall be restored, so far as is practicable, to its condition before the development took place, or restored to such condition as may have been agreed in writing between the mineral planning authority and the developer.