OpenLegislation

Paragraph A.2 Conditions

Changes not yet applied. Later legislation changes this provision in ways not yet written into the text below:

Development is permitted by this class subject to the following conditions—

(a)

no operations shall be carried out between 6pm and 7am;

(b)

no trees on the land shall be removed, felled, lopped or topped and no other thing shall be done on the land likely to harm or damage any trees, unless the mineral planning authority have so agreed in writing;

(c)

before any excavation (other than a borehole) is made, any topsoil and any subsoil shall be separately removed from the land to be excavated and stored separately from other excavated material and from each other;

(d)

within a period of 28 days from the cessation of operations unless the mineral planning authority have, in a particular case, agreed otherwise in writing—

(i)

any structure permitted by Class A and any waste material arising from development permitted by Class A shall be removed from the land,

(ii)

any borehole shall be adequately sealed,

(iii)

any other excavation shall be filled with material from the site,

(iv)

the surface of the land on which any operations have been carried out shall be levelled and any topsoil replaced as the uppermost layer, and

(v)

the land shall, so far as is practicable, be restored to its condition before the development took place, including the carrying out of any necessary seeding and replanting.