# The Town and Country Planning (General Development Procedure) (Amendment) (Wales) Order 2002

W.S.I. 2002/1877 · made 18 July 2002

This Order amends the Town and Country Planning (General Development Procedure) Order 1995 in relation to Wales so as to require any application to a local planning authority in Wales for planning permission for development which involves the construction or installation of one or more antennas for the purpose of operating a telecommunications system to be accompanied by a written declaration that the equipment and installation to which the application relates is so designed that it will, when constructed or installed, operate in full compliance with the requirements of the radio frequency public exposure guidelines of the International Commission on Non-ionising Radiation Protection.

Made under: Town and Country Planning Act 1990 (Section 59, Section 61, Section 65, Section 69, Section 71, Section 73, Section 74, Section 77, Section 78, Section 79, Section 188, Section 193, Section 196, Section 333, Schedule 1 paragraph 5, Schedule 1 paragraph 6, Schedule 1 paragraph 7, Schedule 1 paragraph 8)

PDFs: Printed copy https://openlegislation.uk/town-and-country-planning-general-development-procedure-amendment-wales-order-2002/pdf/wsi_20021877_mi.pdf

## Introductory text

TOWN AND COUNTRY PLANNING, WALES
Made 18th July 2002
Coming into force 1st August 2002
The National Assembly for Wales, in exercise of the powers conferred on the Secretary of State by sections 59, 61(1), 65, 69, 71, 73(3), 74, 77(4), 78, 79(4), 188, 193, 196(4), and 333(7) of, and paragraphs 5, 6, 7(6) and 8(6) of Schedule 1 to, the Town and Country Planning Act 1990 and now exercisable by it and of all other powers enabling it in that behalf, hereby make the following Order:

## 1 Citation, commencement and application

(1) This Order may be cited as the Town and Country Planning (General Development Procedure) (Amendment) (Wales) Order 2002 and comes into force on the 1st August 2002.
(2) This Order applies to Wales.

## 2 Interpretation

In this Order, “the 1995 Order” means the Town and Country Planning (General Development Procedure) Order 1995 and any reference to a numbered article is a reference to the article bearing that number in the 1995 Order.

## 3 Amendment of the 1995 Order

Insert in the 1995 Order, after Article 5—
“Declaration to accompany application to a local planning authority in Wales for planning permission for certain telecommunications developments.
5A (1) This article applies to any application for planning permission which:
(a) is made to a local planning authority in Wales; and
(b) relates to development which involves the construction or installation of one or more antennas for the purpose of operating a telecommunications system .
(2) For the purposes of this Article—
“telecommunications system” has the meaning assigned to that term by section 4(1) of the Telecommunications Act 1984 (meaning of “telecommunications system” and related expressions);
(3) An application to which this Article applies must be accompanied by a written declaration that the equipment and installation to which the application relates is so designed that it will, when constructed or installed, operate, having regard to its location and the manner in which it has been constructed or installed, in full compliance with the requirements of the radio frequency public exposure guidelines of the International Commission on Non-ionising Radiation Protection, as expressed in EU Council recommendation of 12 July 1999 on the limitation of exposure of the general public to electromagnetic fields (0 Hz to 300 GHz).”

## 4 Transitional provisions

The amendments made to the 1995 Order by this Order do not apply in relation to applications for planning permission which are made before this Order comes into force.

## Signature

Signed on behalf of the National Assembly for Wales under section 66(1) of the Government of Wales Act 1998
John Marek
The Deputy Presiding Officer of the Assembly
18th July 2002

## Explanatory note

(This note is not part of the Order)
This Order amends the Town and Country Planning (General Development Procedure) Order 1995 in relation to Wales so as to require any application to a local planning authority in Wales for planning permission for development which involves the construction or installation of one or more antennas for the purpose of operating a telecommunications system to be accompanied by a written declaration that the equipment and installation to which the application relates is so designed that it will, when constructed or installed, operate in full compliance with the requirements of the radio frequency public exposure guidelines of the International Commission on Non-ionising Radiation Protection.
Many forms of development relating to telecommunications apparatus enjoy permitted development rights under Part 24 of Schedule 2 to the Town and Country Planning (General Permitted Development) Order 1995. A requirement for a similar declaration to accompany applications to local planning authorities in Wales for determinations as to whether prior approval is required under that Order where such an application is required in connection with development relating to the construction or installation of one or more antennas is also being introduced by an amendment to that Order.

---
Source: https://www.legislation.gov.uk/wsi/2002/1877 (the official version)
Page: https://openlegislation.uk/town-and-country-planning-general-development-procedure-amendment-wales-order-2002
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.