# The Town and Country Planning (General Permitted Development) (England) Order 2015, Paragraph J: Permitted development


Development on any land during a period not exceeding 28 consecutive days consisting of–
(a) the drilling of boreholes;
(b) the carrying out of seismic surveys; or
(c) the making of other excavations,

---
Source: https://www.legislation.gov.uk/uksi/2015/596/schedule/2/part/17/crossheading/class-j-temporary-use-of-land-etc-for-mineral-exploration/paragraph/J (the official version)
Page: https://openlegislation.uk/town-and-country-planning-general-permitted-development-england-order-2015/schedule-2/part-17/crossheading-class-j-temporary-use-of-land-etc-for-mineral-exploration/paragraph-J
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.