Development on any land during a period not exceeding 28 consecutive days consisting of the drilling of boreholes for the purposes of—
(a) carrying out groundwater monitoring;
(b) carrying out seismic monitoring; or
(c) locating and appraising the condition of mines,
which is preparatory to potential petroleum exploration, and the provision or assembly on that land or adjoining land of any structure required in connection with any of those drilling, monitoring or locating and appraising operations.

---
Source: https://www.legislation.gov.uk/uksi/2015/596/schedule/2/part/17/crossheading/class-ja-temporary-use-of-land-etc-in-respect-of-petroleum-exploration/paragraph/JA (the official version)
Page: https://openlegislation.uk/town-and-country-planning-general-permitted-development-england-order-2015/schedule-2/part-17/crossheading-class-ja-temporary-use-of-land-etc-in-respect-of-petroleum-exploration/paragraph-JA
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.