# The Town and Country Planning (General Permitted Development) (England) Order 2015, Paragraph AC.2: Conditions


(1) Where any development under Class AC is proposed, development is permitted subject to the condition that before beginning the development, the developer must apply to the local planning authority for prior approval of the authority as to—
(a) transport and highways impacts of the development;
(b) air traffic and defence asset impacts of the development;
(c) contamination risks in relation to the building;
(d) flooding risks in relation to the building;
(e) the external appearance of the building, including—
(i) the design and architectural features of—
(aa) the principal elevation; and
(bb) any side elevation that fronts a highway; and
(ii) the impact of any works under paragraph AC(2)(b) or (c);
(f) the provision of adequate natural light in all habitable rooms of the new dwellinghouses;
(g) impact on the amenity of the neighbouring premises including overlooking, privacy and the loss of light;
(h) whether, because of the siting of the building, the development will impact on a protected view identified in the Directions Relating to Protected Vistas dated 15th March 2012 issued by the Secretary of State,
and the provisions of paragraph B (prior approval) of this Part apply in relation to that application.
(2) Any development under Class AC is permitted subject to the following conditions—
(a) the materials used in any exterior work must be of a similar appearance to those used in the construction of the exterior of the existing dwellinghouse;
(b) following the development, the roof pitch of the principal part of the building must be the same as the roof pitch of the principal part of the existing dwellinghouse; and
(c) the development must not include a window in any wall or roof slope forming a side elevation of the dwellinghouse.
(3) Any development under Class AC is permitted subject to the condition that it must be completed within a period of 3 years starting with the date prior approval is granted.
(4) Any development under Class AC is permitted subject to the condition that before beginning the development, the developer must provide the local planning authority with a report for the management of the construction of the development, which sets out the proposed development hours of operation and how any adverse impact of noise, dust, vibration and traffic on occupiers of the building and adjoining owners or occupiers will be mitigated.
(5) The developer must notify the local planning authority of the completion of the development as soon as reasonably practicable after completion.
(6) The notification referred to in sub-paragraph (5) must be in writing and must include—
(a) the name of the developer;
(b) the address or location of the development; and
(c) the date of completion.
(7) Following the development, every dwellinghouse in the building must remain in use as a dwellinghouse within the meaning of Class C3 of the Schedule to the Use Classes Order and for no other purpose, except to the extent that the other purpose is ancillary to the primary use as a dwellinghouse.

---
Source: https://www.legislation.gov.uk/uksi/2015/596/schedule/2/part/20/crossheading/class-ac-new-dwellinghouses-on-terrace-buildings-in-use-as-dwellinghouses/paragraph/AC.2 (the official version)
Page: https://openlegislation.uk/town-and-country-planning-general-permitted-development-england-order-2015/schedule-2/part-20/crossheading-class-ac-new-dwellinghouses-on-terrace-buildings-in-use-as-dwellinghouses/paragraph-AC.2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.