# The Town and Country Planning (General Permitted Development) (England) Order 2015, Paragraph MA.2: Conditions


(1) Development under Class MA is permitted subject to the following conditions.
(2) Before beginning development under Class MA, the developer must apply to the local planning authority for a determination as to whether the prior approval of the authority will be required as to—
(a) transport impacts of the development, particularly to ensure safe site access;
(b) contamination risks in relation to the building;
(c) flooding risks in relation to the building;
(d) impacts of noise from commercial premises on the intended occupiers of the development;
(e) where—
(i) the building is located in a conservation area, and
(ii) the development involves a change of use of the whole or part of the ground floor,
the impact of that change of use on the character or sustainability of the conservation area;
(f) the provision of adequate natural light in all habitable rooms of the dwellinghouses;
(g) the impact on intended occupiers of the development of the introduction of residential use in an area the authority considers to be important for general or heavy industry, waste management, storage and distribution, or a mix of such uses; ...
(h) where the development involves the loss of services provided by—
(i) a registered nursery, or
(ii) a health centre maintained under section 2 or 3 of the National Health Service Act 2006,
the impact on the local provision of the type of services lost ; and
(i) where the development meets the fire risk condition, the fire safety impacts on the intended occupants of the building
(3) An application for prior approval for development under Class MA may not be made before 1 August 2021.
(4) The provisions of paragraph W (prior approval) of this Part apply in relation to an application under this paragraph as if—
(a) for paragraph (e) of sub-paragraph (2) there were substituted—
“(e) where—
(i) sub-paragraph (6) requires the Environment Agency to be consulted, a site-specific flood risk assessment;
(ii) sub-paragraph (6A) requires the Building Safety Regulator to be consulted, a statement about the fire safety design principles, concepts and standards that have been applied to the development,”;
(b) in the introductory words in sub-paragraph (5), for “and highways impacts of the development” there were substituted “impacts of the development, particularly to ensure safe site access”;
(c) after sub-paragraph (6) there were inserted—
“(6A) Where the application relates to prior approval as to fire safety impacts, on receipt of the application, the local planning authority must consult the Building Safety Regulator.”;
(d) in sub-paragraph (7) for “(5) and (6)” there were substituted “(5), (6) and (6A)”;
(5) Development must be completed within a period of 3 years starting with the prior approval date.
(6) Any building permitted to be used as a dwellinghouse by virtue of Class MA is to remain in use as a dwellinghouse within the meaning of Class C3 of Schedule 1 to the Use Classes Order and for no other purpose, except to the extent that the other purpose is ancillary to the use as a dwellinghouse.

---
Source: https://www.legislation.gov.uk/uksi/2015/596/schedule/2/part/3/crossheading/class-ma-commercial-business-and-service-uses-to-dwellinghouses/paragraph/MA.2 (the official version)
Page: https://openlegislation.uk/town-and-country-planning-general-permitted-development-england-order-2015/schedule-2/part-3/crossheading-class-ma-commercial-business-and-service-uses-to-dwellinghouses/paragraph-MA.2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.