(1) Development under Class O is permitted subject to the condition that before beginning the development, the developer must apply to the local planning authority for a determination as to whether the prior approval of the authority will be required as to—
(a) transport and highways impacts of the development,
(b) contamination risks on the site,
(c) flooding risks on the site, ...
(d) impacts of noise from commercial premises on the intended occupiers of the development , and
(e) the provision of adequate natural light in all habitable rooms of the dwellinghouses.
and the provisions of paragraph W (prior approval) apply in relation to that application.
(2) Development under Class O is permitted subject to the following conditions—
(a) the development must be completed within a period of 3 years starting with the prior approval date; and
(b) the developer must apply for a determination under sub-paragraph (1) on or before 31st July 2021

---
Source: https://www.legislation.gov.uk/uksi/2015/596/schedule/2/part/3/crossheading/class-o-offices-to-dwellinghouses/paragraph/O.2 (the official version)
Page: https://openlegislation.uk/town-and-country-planning-general-permitted-development-england-order-2015/schedule-2/part-3/crossheading-class-o-offices-to-dwellinghouses/paragraph-O.2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.