# The Town and Country Planning (General Permitted Development) (England) Order 2015, Paragraph CA.3: Interpretation of Class CA


For the purposes of Class CA—
“academic year”, “relevant Minister” and “state-funded school” have the meanings given in paragraph C.3;
“prior approval date” means the date on which—
(a)prior approval is given; or
(b)a determination that such prior approval is not required is given or the period for giving such a determination set out in paragraph W(11)(c) of Part 3 of this Schedule (as applied with modifications by paragraph CA.2(2)) has expired without the applicant being notified whether prior approval is required, given or refused; and
“vacant commercial land” means any land on which—
(a)all buildings have been demolished; and
(b) which was last used for a purpose falling within one of the following provisions of the Use Classes Order—
(i)Class C1 (hotels) of Schedule 1;
(ii)Class C2 (residential institutions) of Schedule 1;
(iii)Class C2A (secure residential institutions) of Schedule 1;
(iv)Class E (commercial, business and service) of Schedule 2.

---
Source: https://www.legislation.gov.uk/uksi/2015/596/schedule/2/part/4/crossheading/class-ca-provision-of-a-temporary-statefunded-school-on-previously-vacant-commercial-land/paragraph/CA.3 (the official version)
Page: https://openlegislation.uk/town-and-country-planning-general-permitted-development-england-order-2015/schedule-2/part-4/crossheading-class-ca-provision-of-a-temporary-statefunded-school-on-previously-vacant-commercial-land/paragraph-CA.3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.