Development consisting of—
(a) the temporary use of any land or buildings for a period not exceeding 12 months in any 27 month period for the purpose of commercial film-making; and
(b) the provision on such land, during the filming period, of any temporary structures, works, plant or machinery required in connection with that use.

---