# The Town and Country Planning (General Permitted Development) (England) Order 2015, Paragraph I: Permitted development


Development carried out on industrial land for the purposes of an industrial process consisting of—
(a) the installation of additional or replacement plant or machinery;
(b) the provision, rearrangement or replacement of a sewer, main, pipe, cable or other apparatus, or
(c) >the provision, rearrangement or replacement of a private way, private railway, siding or conveyor.

---
Source: https://www.legislation.gov.uk/uksi/2015/596/schedule/2/part/7/crossheading/class-i-developments-relating-to-an-industrial-process/paragraph/I (the official version)
Page: https://openlegislation.uk/town-and-country-planning-general-permitted-development-england-order-2015/schedule-2/part-7/crossheading-class-i-developments-relating-to-an-industrial-process/paragraph-I
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.