Development is permitted by Class M subject to the following conditions—
(a) the development is within the curtilage of an existing school, college, university , prison or hospital;
(b) the development is only used as part of, or for a purpose incidental to, the use of that school, college, university , prison or hospital;
(c) any new building erected is, in the case of article 2(3) land, constructed using materials which have a similar external appearance to those used for the original school, college, university , prison or hospital buildings; ...
(d) any extension or alteration is, in the case of article 2(3) land, constructed using materials which have a similar external appearance to those used for the building being extended or altered ;
(e) where proposed development under Class M relates to the erection, extension or alteration of a school building that results in an increase in the school’s published admission number, the developer must, within a period of six months starting with the date the development is completed, submit to the local planning authority a travel plan for the site;
(f) where proposed development under Class M relates to the erection, extension or alteration of a university building, development is permitted subject to the condition that before beginning the development the developer applies to the local planning authority for a determination as to whether the prior approval of the authority will be required as to—
(i) transport and highways impacts of the proposed development;
(ii) the design and external appearance of the erection, extension or alteration; or
(iii) the impact of the development on heritage and archaeology;
(g) an application required under paragraph (f) is to be made and determined in accordance with paragraph M.2A (procedure for applications for prior approval under Class M);
(h) development approved pursuant to an application under paragraph (f) is permitted subject to the condition that it is completed within a period of three years starting with the prior approval date;
(i) where proposed development under Class M relates to the erection, extension or alteration of an open prison building, before beginning development the developer must—
(i) assess the contamination and flood risks of the development;
(ii) identify measures to reduce, so far as practicable, any contamination or flood risks of the development;
(iii) where the development is in an area within Flood Zone 3, carry out prior consultation in accordance with paragraph M.2B (procedure for prior consultation under Class M); and
(iv) provide written notification to the local planning authority of the proposed development with the documents and information listed in sub-paragraph (j);
(j) the documents and information specified in sub-paragraph (i)(iv) are—
(i) a written description of the proposed development;
(ii) a plan indicating the site and showing the proposed development;
(iii) a drawing, prepared to an identified scale, showing—
(aa) in the case of a building to be erected, the proposed external dimensions and elevations of that building; and
(bb) in the case of a building to be extended or altered, the external dimensions and elevations of that building both before and after the proposed extension or alteration;
(iv) the proposed commencement date;
(v) written confirmation that development will not take place on any land used as a playing field, and remaining in that use, at any time in the 5 years before the proposed commencement date;
(vi) the developer’s contact address; and
(vii) the developer’s email address if the developer is content to receive communications electronically.

---
Source: https://www.legislation.gov.uk/uksi/2015/596/schedule/2/part/7/crossheading/class-m-extensions-etc-for-schools-colleges-universities-and-hospitals/paragraph/M.2 (the official version)
Page: https://openlegislation.uk/town-and-country-planning-general-permitted-development-england-order-2015/schedule-2/part-7/crossheading-class-m-extensions-etc-for-schools-colleges-universities-and-hospitals/paragraph-M.2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.