Regulation 61 Pause of independent examination for further work
The period prescribed for the purposes of section 15DA(3)(b) of the Act (the pause period), in relation to the examination of a minerals and waste plan document, is six months.
As soon as is reasonably practicable after receiving a notification under section 15DA(2) of the Act, the minerals and waste planning authority must notify each person who requested to be so notified of the decision of the examiner under section 15D(7) of the Act.
A minerals and waste planning authority must comply with section 15DA(7) of the Act as soon as is reasonably practicable after complying with section 15DA(6).
When a minerals and waste planning authority comply with section 15DA(7) of the Act, the authority must on the same day—
make the document and evidence sent to the examiner under section 15DA(6) of the Act available in accordance with regulation 88, and
notify each person to whom notification was sent in accordance with paragraph (2) that the document and evidence are available for inspection and of the places and times at which they can be inspected.
A minerals and waste planning authority must comply with section 15DA(10) of the Act as soon as is reasonably practicable after receipt of the recommendations and reasons of the examiner under section 15DA(8).
When a minerals and waste planning authority comply with section 15DA(10) of the Act, the authority must on the same day—
make the recommendations and reasons of the examiner available in accordance with regulation 88, and
notify each person to whom notification was sent in accordance with paragraph (2) that the recommendations and reasons of the examiner are available for inspection and of the places and times at which they can be inspected.