OpenLegislation

Regulation 9 Publication of a minerals and waste plan timetable

Original text. Later amendments are not shown.

(1)

A minerals and waste planning authority must first comply with section 15B(8) of the Act in relation to a minerals and waste plan timetable no later than on the earlier of—

(a)

the date on which the authority make their notice of intention to commence minerals and waste plan document preparation available under regulation 44(1) for the first minerals and waste plan document which the authority are to prepare, or

(b)

the date on which the authority make a notice of intention to commence supplementary plan preparation available under regulation 68(1).

(2)

When a minerals and waste planning authority comply with section 15B(8) of the Act, the authority must on the same day make available in accordance with regulation 88—

(a)

their minerals and waste plan timetable, and

(b)

the statement that the timetable is to have effect.