# The Town and Country Planning (Major Infrastructure Project Inquiries Procedure) (England) Rules 2002, Paragraph 8: Descriptions of Major Infrastructure Project


Dams and other installations designed for the holding back or permanent storage of water, where a new or additional amount of water held back or stored exceeds 10 million cubic metres.

---
Source: https://www.legislation.gov.uk/uksi/2002/1223/schedule/paragraph/8 (the official version)
Page: https://openlegislation.uk/town-and-country-planning-major-infrastructure-project-inquiries-procedure-england-rules-2002/schedule/paragraph-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.