(1) Development permitted by article 3(1)(e) may not commence until the following conditions are complied with—
(a) the design and materials specifications of—
(i) the proposed surface construction, and
(ii) its surface water drainage system,
are approved in writing by the Secretary of State;
(b) an unexploded ordnance survey is conducted in the area marked “B” and shaded in red on the map; and
(c) an archaeological survey is conducted in the area marked “B” and shaded in red on the map.
(2) Prior to the removal or disturbance of the Y-shaped dispersal pads in the area marked on the map as “B” and shaded in red, those dispersal pads must be appropriately recorded in accordance with Historic England’s technical guidance or alternative best practice.

---
Source: https://www.legislation.gov.uk/uksi/2019/86/article/8 (the official version)
Page: https://openlegislation.uk/town-and-country-planning-manston-airport-special-development-order-2019/article-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.