Article 11 Transitional provisions
Paragraph (2) applies in relation to an application for planning permission—
which falls within Category 3D of the Schedule to the 2008 Order,
which is sent to the Mayor under article 5(1)(a) of the 2008 Order before the commencement date, and
in relation to which, before the commencement date, the Mayor is not permitted to give a direction under section 2A of the 1990 Act that he is to be the local planning authority for the purposes of determining the application.
Where this paragraph applies, notwithstanding the amendment made by article 10(2), the Mayor may not give a direction under section 2A of the 1990 Act that he is to be the local planning authority for the purposes of determining the application.
Paragraph (4) applies in relation to an application for planning permission which—
is received by the local planning authority before the commencement date, and
does not meet the definition of “PSI application” in the 2008 Order as it has effect immediately before the commencement date.
Where this paragraph applies, notwithstanding the amendment made by article 10(4), the local planning authority is not required to notify the Mayor of the application under article 4(1) of the 2008 Order.
The amendments made by this Order do not apply in relation to a section 73 application where the previous planning permission was granted before the commencement date.