Article 3 Temporary planning permission

Original text. Later amendments are not shown.

(1)

Subject to articles 4 and 5, planning permission is granted for development on the land consisting of—

(a)

use of the land for the stationing and processing of vehicles;

(b)

use of the land for repairs to goods vehicles where a vehicle examiner—

(i)

examines the vehicle on the land;

(ii)

determines, pursuant to section 69(1) of the Road Traffic Act 1988, that owing to any defects in the vehicle it is, or is likely to become, unfit for service, and

(iii)

prohibits the driving of the vehicle on a road;

(c)

re-alignment of the egress point and increasing the road width of the egress point;

(d)

provision on the land of new temporary structures, works, plant or machinery and lighting, including—

(i)

for the use permitted by sub-paragraph (a), the provision of facilities for drivers of vehicles, and

(ii)

the provision of temporary structures (including portacabins) for administration and other facilities for persons processing vehicles;

(e)

resurfacing and repair of hard standing and rough gravelled area adjacent to the pre-existing hard standing; and

(f)

repair of the foul water and surface water drainage systems on the land.

(2)

The planning permission granted by paragraph (1) ceases at the end of 31st December 2020 and immediately thereafter the land reverts to its previous lawful use.