# The Transport and Works (Applications and Objections Procedure) (England and Wales) Rules 2006, Part 1: Table of Fees


(1)
(2)
Subject- matter of application
Fee
1 Construction of a transport system or inland waterway which would involve any compulsory acquisition of land but would not involve any interference with rights of navigation.
1
(i) For the first hectare or part hectare of the proposed works, £6,600.
(ii) For the next 49 hectares, £1,100 per hectare or part hectare.
(iii) For the next 50 hectares, £550 per hectare or part hectare.
(iv) For any additional area, £275 per hectare or part hectare.
2 Construction of a transport system or inland waterway which would not require the compulsory acquisition of land and not interfere with rights of navigation.
2
(i) For the first hectare or part hectare of the proposed works, £4,400.
(ii) For the next 49 hectares, £550 per hectare or part hectare.
(iii) For any additional area, £110 per hectare or part hectare.
3 Construction of works any part of which would involve interference with rights of navigation, being of a description prescribed under section 4.
3
(a) Where the works to be constructed would not form part of a transport system, an inland waterway or a wind farm—
(i) for the first hectare or part hectare of the proposed works, £8,800;
(ii) for the next 49 hectares, £1,650 per hectare or part hectare;
(iii) for the next 50 hectares, £825 per hectare or part hectare; and
(iv) for any additional area, £412 per hectare or part hectare.
(b) Where the works to be constructed include works which would form part of a transport system or an inland waterway—
(i) for works which would interfere with rights of navigation, as in paragraph 3(a), and
(ii) for other works, as in paragraph 1(ii), (iii) or (iv), or 2(ii) or (iii), as applicable.
(c) Where the works to be constructed would form part of a wind farm—
(i) for a wind farm comprising up to 30 wind turbines, £20,000; and
(ii) for a wind farm comprising 31 or more wind turbines, £20,000 for the first 30 wind turbines plus £500 for each additional wind turbine.
4 Provision for the transfer of an undertaking.
4 £2,000.
5 Provision for any matter other than those described above.
5 £4,000.

---
Source: https://www.legislation.gov.uk/uksi/2006/1466/schedule/4/part/1 (the official version)
Page: https://openlegislation.uk/transport-and-works-applications-and-objections-procedure-england-and-wales-rules-2006/schedule-4/part-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.