# The Transport for Greater Manchester (Light Rapid Transit System) (Second City Crossing) Order 2013, Schedule 6: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

Extent: E+W

(1)
Location
(2)
Number of land shown on the works and land plans
(3)
Purpose for which temporary possession may be taken
(4)
Scheduled work
Windmill Street (including part of the forecourt to Manchester Central Convention Complex and service road to the Midland Hotel)
1001, 1002, 1003
Highway works, temporary tramway works & construction working area.
Work No. 1
Oxford Street (between Peter Street and Portland Street)
1021, 1022, 1024, 1027
Highway works.
Work No. 1
Hall Street (at its junction with Oxford Street)
1023
Highway works.
Work No. 1
St. James Street (at its junction with Oxford Street)
1025
Highway works.
Work No. 1
George Street (at its junction with Oxford Street)
1026
Highway works.
Work No. 1
Peter Street (opposite West Mosley Street and the Central Public Library)
1030
Highway works.
Work No. 1
St Peter’s Square (including the land in front of Elisabeth House)
1027, 1037
Landscaping works.
Work No. 1
Dickinson Street (between Back George Street and St Peter’s Square)
1027, 1038
Highway & landscaping works.
Work No. 1
Back George Street (at its junction with Dickinson Street)
1038
Highway works.
Work No. 1
West Mosley Street (including the land in front of the Central Public Library and Town Hall Extension)
1031, 1032
Landscaping works.
Work No. 1
Princess Street (at its junction with Portland Street)
1107
Highway works
Work No. 2
Portland Street (at its junction with Princess Street)
1106
Highway works
Work No. 2
Princess Street (between George Street and Mosley Street)
1044
Highway works.
Work No. 2
West Mosley Street (at its junction with Princess Street)
1050
Highway works.
Work No. 2
Cooper Street (between Princess Street and Kennedy Street)
1052
Highway works.
Work No. 2
Bow Lane (at its junction with Princess Street)
1061
Highway works.
Work No. 2
Clarence Street (between Princess Street and Bow Lane)
1066
Highway works.
Work No. 2
Albert Square (between Lloyd Street and John Dalton Street)
1069
Highway & landscaping works.
Work No. 2
John Dalton Street (between Ridgefield and Albert Square / Princess Street / Cross Street)
1074
Highway works.
Work No. 2
Bow Lane (at its junction with Cross Street)
1075
Highway works.
Work No. 2
Tib Lane (at its junction with Cross Street)
1081
Highway works.
Work No.2
Town Hall Lane (at its junction with Cross Street)
1083
Highway works.
Work No. 2
South King Street (between Cross Street and St James’s Square)
1080
Highway works.
Work No. 2
King Street (at its junction with Cross Street)
1089
Highway works.
Work No. 2
King Street (between Cross Street and Brown Street including its junction with Essex Street and Cheapside)
1097
Highway works.
Work No. 2
Chapel Walks (at its junction with Cross Street)
1103, 2005
Highway works.
Work No. 2
Back Pool Fold (at its junction with Cross Street)
2007
Highway works.
Work No. 2
Old Bank Street (at its junction with Cross Street)
2009
Highway works.
Work No. 2
Market Street (between Corporation Street and Exchange Street / St Mary’s Gate)
2019, 2020
Highway works.
Work No. 2
Exchange Street (at its junction with St Mary’s Gate / Market Street)
2015
Highway works.
Work No. 2
St Mary’s Gate (at is junction with Market Street / Exchange Street)
2019
Highway works.
Work No. 2
Market Street (to the east of its junction with Cross Street / Corporation Street)
2017
Highway works.
Work No. 2
Corporation Street (entrance steps to Arndale Centre)
2036
Highway & landscaping works.
Work No. 3
Cateaton Street (between Deansgate and Hanging Ditch)/
2039
Highway & landscaping works.
Work No. 3
Exchange Square (including Hanging Ditch)
2039, 2040, 2041, 2042
Landscaping works.
Work No. 3
Withy Grove (between Corporation Street and Dantzic Street)
2050
Highway works.
Work No. 3
Well Street (between Dantzic Street, Withy Grove and Garden Street)
2050
Highway works.
Work No. 3
Garden Street (between Well Street and Dantzic Street)
2050
Highway works.
Work No. 3
Dantzic Street (between Withy Grove and Well Street)
2050
Highway works.
Work No.3
Fennel Street (at its junction with Corporation Street)
2048
Highway works.
Work No. 3
Unnamed Access (to the Printworks) and adjoining land
2058, 2059, 2060
Highway works.
Work No. 3
Corporation Street (between Balloon Street and Hanover Street)
2068
Highway works.
Work No. 3

---
Source: https://www.legislation.gov.uk/uksi/2013/2587/schedule/6 (the official version)
Page: https://openlegislation.uk/transport-for-greater-manchester-light-rapid-transit-system-second-city-crossing-order-2013/schedule-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.